Water

Multi-purpose Reservoir

GENDER SENSITIVITY

 

URBAN-RURAL CONNECTIVITY

 

CLIMATE SENSITIVITY

 

PIDA PROGRAMME:
44 - Gourbassi Multipurpose Dam

LATEST ACTUAL STAGE:

S3A: Project Structuring (2017)

PROJECT LOCATION

Mali Senegal

PROJECT INSTITUTION:

Organisation pour la Mise en Valeur du Fleuve Sénégal

BENEFICARY COUNTRIES

Mali

Senegal

PROJECT DIMENSIONS:

Reservoir Capacity: 3 km3

STARTING_DATE:

COMPLETION_DATE:

PREPARATION COST:

15.00 million USD

CAPEX COST:

298.00 million USD

PROJECT STAGE:

S3A: Project Structuring

PROJECT FEATURED IN:

Koukoutamba (ex-Gourbassy) Multi-purpose Dam

Construction of the Koukoutamba (ex-Gourbassy) Dam to regulate the Senegal River in four countries via a multipurpose dam located in Guinea. The project will include an electricity generation component in Mali and Senegal.

DESCRIPTION

The project involves the construction of the Koukoutamba multi-purpose dam (previously known as Gourbassy dam) between Mali and Senegal.

A feasibility study and preliminary design for the Gourbassy Dam was completed by SNC LAVALIN International in 2012 for the OMVS Secretariat (Haut Commissariat de l’OMVS), with funding from the World Bank under the project PGIRE 1. The main summary report is dated July 2012.

Since then, some (rather modest) progress has been made on further project preparation and mobilisation of finance. Activities that have been undertaken include: preparation of terms of reference for detailed design studies and tender documents. The preparation of studies to assess the cost of building the dam; and development of plans to mobilise finance, including planning for a donor round table and sending out funding requests to potential partners has been done.

OBJECTIVES AND RATIONALE

PROJECT RISKS

PROJECT ECONOMICS

  • NET PRESENT VALUE: 0.00
  • COST BENEFIT RATIO: 0.00
  • FINANCIAL INTERNAL RATE OF RETURN (FIRR): 0.00
  • ECONOMIC INTERNAL RATE OF RETURN (EIRR): 0.00
  • COMMENTS ON ECONOMICS:

PROJECT FINANCING

PREPARATION CAPEX
COST: 15.00 298.00
COST SECURED: 0.00 0.00
FINANCING TYPE:
FINANCIERS:
OPERATION AND MAINTENANCE
OVERALL COST: 0.00
ANNUAL COST: 0.00
COMMENTS ON FINANCE:
Funding for the feasibility study received from the World Bank under the project Integrated Water Resources Management and Multipurpose Use Development Project (PGIRE 1).
Development of plans to mobilise finance has commenced, including planning for a donor round table and sending out funding requests to potential partners

STUDIES

PROJECT STAKEHOLDERS

Regional Coordinator

Economic Community of West African States

Sectoral Organisation

Global Water Partnership

Lead National Agency

Organisation pour la Mise en Valeur du Fleuve Sénégal

CONTACTS

Mr Madine Ba-omvssphc@omvs.org

Mr Marimantia Diarra-omvssphc@omvs.org

Mr Kabiné Komara-omvssphc@omvs.org

Mr. Peter Ofori-Asumadu -poasumadu@yahoo.com

CONTRIBUTION TO 2030 AGENDA