LATEST ACTUAL STAGE:
S4C: Operation (2022)PROJECT LOCATION
BurundiPROJECT INSTITUTION:
DRC - Le bureau des RoutesBENEFICARY COUNTRIES
BurundiPROJECT DIMENSIONS:
Length: 56 km Commercial Traffic Throughput: 47 vehicles/daySTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
0.00 million USDCAPEX COST:
50.00 million USDPROJECT STAGE:
S4C: Operation
PROJECT FEATURED IN:
The national road 18: Nyakararo-Mwaro-Gitega (56 km) is a missing link of the Central Corridor Bujumbura-Mwaro-Gitega-Kobero (Burundi)/Kabanga-Dodoma-Dar Es Salaam (Tanzania). Until 2015, the road was still in gravel. From 2016, it is being upgraded and widened from 6m to 7m. The first lot: Nyakararo-Mwaro-Kibumbu (26 km) is completed. The remaining lot: Kibumbu-Mweya-Gitega will also be upgraded with AfDB funds.
RN18 is a 56km road on the Central Corridor along the RN7- RN18- RN16 route and is a conduit for movement of traffic from Tanzania to Gitega and Bujumbura. RN18 requires upgrading from gravel to asphalt concrete and expansion of the carriageway from 6 metres to 7 metres.
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 0.00 | 50.00 |
| COST SECURED: | 0.00 | 0.00 |
| FINANCING TYPE: | Grant Only | Grant Only |
| FINANCIERS: |
Central Corridor Transit Transport Facilitation Agency
DRC - Le bureau des Routes
Burundi Ministry of Transport, Public Works and Equipment
East African Community
PIDA CAP Expert Bayihishako Pierre-PierreB@nepad.org; bapierresimon@yahoo.fr
Infrastructure Specialist Sabiiti Charles Habarugira-Charless@centralcorridor-ttfa.org; csabiiti@yahoo.co.uk
Chef du Service Planification Routiere Burundibusha Innocent-bushabu@yahoo.fr
Infrastructure Expert (NEPAD) Mr. David Niyonsenga -DavidN@nepad.org
Infrastructure Expert (NEPAD) Mr. Pierre Bayihishako-SnowdenM@nepad.org