LATEST ACTUAL STAGE:
S2B: Feasibility (2019)PROJECT LOCATION
ZimbabwePROJECT INSTITUTION:
BENEFICARY COUNTRIES
Malawi Mozambique South Africa ZimbabwePROJECT DIMENSIONS:
Length: 215 km Design Life: 20 Yrs Design Speed: 120 km/h Number of Lanes: 2 lanesSTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
0.66 million USDCAPEX COST:
93.00 million USDPROJECT STAGE:
S2B: Feasibility
PROJECT FEATURED IN:
Rehabilitation and upgrading of the 215 km Harare - Nyamapanda road in Zimbabwe, to Nyamapanda/Cuchimano Border Post.
The road runs in a north-easterly direction from Harare to the Nyamanpanda Border Post (between Zimbabwe and Mozambique), covering a total distance of 278km. See this project on an interactive GIS map (with Google Earth satellite imagery and geo-referenced photographs) at www.tmsagis.co.za.
The Harare-Nyamapanda road is part of the Regional Trunk Road Network (RTRN Link NR 25) as well as the Trans-African Highway NR 9 and the rehabilitation of Marehwa-Nyamapanda is a section of this project, which covers a distance of 172km.
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 0.66 | 93.00 |
| COST SECURED: | 0.00 | 0.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
Tripartite Project Preparation and Implementation Unit
Southern African Development Community
Zimbabwe - Ministry of Transport and Infrastructural Development
African Union Development Agency
Eng Theodius Kudzanayi CHINYANGA-theodiuskchinyanga@gmail.com
Infrastructure Expert Mr. Edvan Moyo-edmoyo@sadc.int