LATEST ACTUAL STAGE:
S4C: Operation (2024)PROJECT LOCATION
KenyaPROJECT INSTITUTION:
Kenya Power and Lighting CompanyBENEFICARY COUNTRIES
Kenya Tanzania ZambiaPROJECT DIMENSIONS:
Voltage: 400 kVSTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
12.00 million USDCAPEX COST:
50.00 million USDPROJECT STAGE:
S4C: Operation
PROJECT FEATURED IN:
Construction of 96 km / 400 kV Kenya section of the ZTK transmission interconnector.
Construction of a transmission line that connects the power networks of Zambia, Tanzania and Kenya. This project includes the section of 96km Kenyan section of the 2,800km ZTK interconnector from Arush in Tanzania to Isinya in Kenya. In Kenya, the line will be linked to the High Voltage Direct Current Interconnector between Kenya and Ethiopia.
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 12.00 | 50.00 |
| COST SECURED: | 0.00 | 50.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
African Union Development Agency
Common Market for Eastern and Southern Africa
East African Community
Eastern Africa Power Pool
Kenya Power and Lighting Company
Nile Equatorial Lakes Subsidiary Action Program
Mr. Malama Chileshe-mchileshe@comesa.int
Mr. Snowden Mmadi -SnowdenM@nepad.org
Clement Sasa,-csasa@zamnet.zm