LATEST ACTUAL STAGE:
S3A: Project Structuring (2017)PROJECT LOCATION
MalawiPROJECT INSTITUTION:
Malawi - Electricity Supply Corporation of Malawi Mozambique - Electricidade de MocambiqueBENEFICARY COUNTRIES
Malawi MozambiquePROJECT DIMENSIONS:
Voltage: 400 kVSTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
2.00 million USDCAPEX COST:
0.00 million USDPROJECT STAGE:
S3A: Project Structuring
PROJECT FEATURED IN:
Construction of Malawi section approximately 200 km of 400 kV (initial operation at 220 kV) Mozambique-Malawi transmission interconnector, which will connect Malawi to the Southern Africa Power Pool (SAPP).
The project entails the construction of a 200 km, 400 kV(initially 220 kV) power line from Matambo substation, in Mozambique, to Phombeya, north of Blantyre. The first assignment will involve the design, supply and installation of the 400 kV overhead transmission line from the Mozambique-Malawi border to a new substation at Phombeya. The second assignment will entail the design, supply and installation of the new 400 kV Phombeya substation. Other assignments include extension of Matambo substation (Mozambique) and upgrading of SCADA systems (EDM).
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 2.00 | 0.00 |
| COST SECURED: | 0.00 | 0.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
Malawi - Electricity Supply Corporation of Malawi
Malawi - Ministry of Natural Resources, Energy and Mining
Mozambique - Electricidade de Mocambique
Southern African Development Community
Southern African Power Pool
World Bank
Charles Kagona-ckagona@escom.mw
Olga Utchawo-Olga.Utchavo@edm.co.mz
Mr. Ahid Maeresera -ahidm@nepad.org
Cornwell Chisale-cchisale@energy.gov.mw