LATEST ACTUAL STAGE:
S2A: Pre-Feasibility (2022)PROJECT LOCATION
MozambiquePROJECT INSTITUTION:
Mozambique - Electricidade de Mocambique Zambia Electricity Supply CompanyBENEFICARY COUNTRIES
Mozambique ZambiaPROJECT DIMENSIONS:
Voltage: 400 kV Power: 900 MWSTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
12.00 million USDCAPEX COST:
120.00 million USDPROJECT STAGE:
S2A: Pre-Feasibility
PROJECT FEATURED IN:
The Mozambique-Zambia Interconnector will consist of a high voltage transmission line from Chipata 330/132/33 kV substation to the proposed Cataxa substation in Mozambique. The transmission voltage will either be 330 kV or 400 kV. The total line length is estimated at 286 km of which 77 km is in Zambia and the rest in Mozambique.
Construction of a transmission line that connects Cahora Bassa Hydroelectric Power Station at Songo in Mozambique with the power system of Zambia at Serenje.
Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 12.00 | 120.00 |
| COST SECURED: | 0.00 | 0.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
Southern African Development Community
Mozambique - Electricidade de Mocambique
Southern African Power Pool
Zambia Electricity Supply Company
Senior Transaction Advisor Omar Vajeth-omar.vajeth@sapp-pau.com
Project Manager Kennedy Mwanza-kmwanza@zesco.co.zm
Infrastructure Expert (NEPAD) Mr. Ahid Maeresera -ahidm@nepad.org