LATEST ACTUAL STAGE:
S3B: Transaction Support & Financial Close (2018)PROJECT LOCATION
TanzaniaPROJECT INSTITUTION:
Tanzania National Roads AgencyBENEFICARY COUNTRIES
TanzaniaPROJECT DIMENSIONS:
Length: 91 km Number of Lanes: 2 lanesSTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
7.00 million USDCAPEX COST:
73.00 million USDPROJECT STAGE:
S3B: Transaction Support & Financial Close
PROJECT FEATURED IN:
Rehabilitation of 91 km of single carriageway road between Lusahunga and Rusumo in Tanzania.
Rehabilitation of 91 km of single carriageway road between Lusahunga and Rusumo in Tanzania.
Environmental Risks: Limited Social Risks: Not Reported Socio-Enviro Classification: C - minimal social and environmental impacts Other External Risks: Not Reported
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 7.00 | 73.00 |
| COST SECURED: | 0.00 | 0.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
East African Community
Tanzania National Roads Agency
Central Corridor Transit Transport Facilitation Agency
Infrastructure Expert (NEPAD) Mr. David Niyonsenga -DavidN@nepad.org
Infrastructure Expert (NEPAD) Mr. Pierre Bayihishako-SnowdenM@nepad.org