LATEST ACTUAL STAGE:
S4A: Tendering (2013)PROJECT LOCATION
TogoPROJECT INSTITUTION:
BENEFICARY COUNTRIES
Benin TogoPROJECT DIMENSIONS:
STARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
1.70 million USDCAPEX COST:
17.00 million USDPROJECT STAGE:
S4A: Tendering
PROJECT FEATURED IN:
Construction of Ouidah/Hillacondji/Sanveekondji One-Stop Border Post between Togo and Benin.
Construction of Ouidah/Hillacondji/Sanveekondji One-Stop Border Post between Togo and Benin. This part of the project relates specifically to the facilities in Togo.
Social Risks: Health risks due to workers staying in the community
Socio-Enviro Classification: B - limited and/or reversible social and environmental impacts
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 1.70 | 17.00 |
| COST SECURED: | 0.00 | 17.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
Economic Community of West African States
Organisation du Corridor Abidjan-Lagos
African Development Bank
Infrastructure Expert (COMESA) Mr. Peter Ofori-Asumadu -poasumadu@yahoo.com