LATEST ACTUAL STAGE:
S4B: Construction (2013)PROJECT LOCATION
MozambiquePROJECT INSTITUTION:
Mozambique - Caminhos de Ferro de MoçambiqueBENEFICARY COUNTRIES
MozambiquePROJECT DIMENSIONS:
Goods Throughput: 50 mtpaSTARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
0.00 million USDCAPEX COST:
1700.00 million USDPROJECT STAGE:
S4B: Construction
PROJECT FEATURED IN:
*** DISCLAIMER: Project information is incomplete. It will be updated regularly as revisions become available. ***Rehabilitation and Dredging of Maputo and Matola Port (Mozambique)
Expansion of the Maputo port, including the dredging of the port from its current 9,4 m draught to 11 m to accommodate the larger Panamax vessels, which will improve the port’s competitiveness in terms of bulk and container traffic, and expansion of the coal terminal.
Environmental Risks: Not Reported Social Risks: Not Reported Socio-Enviro Classification: Not Reported Other External Risks: Not Reported
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 0.00 | 1700.00 |
| COST SECURED: | 0.00 | 0.00 |
| FINANCING TYPE: | ||
| FINANCIERS: |
Southern African Development Community
Mozambique - Caminhos de Ferro de Moçambique
Mozambique - Ministério dos Transportes e Comunicações
Infrastructure Expert (NEPAD) Mr. Ahid Maeresera -ahidm@nepad.org