LATEST ACTUAL STAGE:
S2A: Pre-Feasibility (2017)PROJECT LOCATION
Cameroon Equatorial GuineaPROJECT INSTITUTION:
Cameroon - Direction Générale des Grands Travaux: Direction des Routes Equatorial Guinea - Ministère de la CommunicationBENEFICARY COUNTRIES
Cameroon Equatorial Guinea GabonPROJECT DIMENSIONS:
STARTING_DATE:
COMPLETION_DATE:
PREPARATION COST:
4.01 million USDCAPEX COST:
0.00 million USDPROJECT STAGE:
S2A: Pre-Feasibility
PROJECT FEATURED IN:
The project concerns the design of a bridge over the Ntem River along the Kribi-Campo-Bata multinational road axis to connect the Kribi-Campo and Campo-Bata road sections. This will be along the Yaounde-Bata-Brazzaville corridor, facilitating linkages between Cameroon and Equatorial Guinea.
The study of the Ntem River Bridge is part of the Kribi-Campo-Bata maritime route linking the port of Kribi to Cameroon and Bata in Equatorial Guinea. The inter-capital connections study will identify missing links and determine the technical and economic feasibility of the construction of a crossing structure and the development of a single border control post at the border of Cameroon and Equatorial Guinea. It will make technical, legal and financial recommendations for the management and operation of the Yaounde-Kribi-Bata-Libreville development and corridor.
| PREPARATION | CAPEX | |
|---|---|---|
| COST: | 4.01 | 0.00 |
| COST SECURED: | 4.01 | 0.00 |
| FINANCING TYPE: | Grant-Equity Blend | |
| FINANCIERS: |
Economic Community of Central African States
Cameroon - Direction Générale des Grands Travaux: Direction des Routes
Equatorial Guinea - Ministère de la Communication
African Development Bank
Chef de service des Transports Jean claude Azonfack-azonfackjc@yahoo.fr